|
As part of its HVAC system, the University had
a large thermal energy storage system and associated
chilled loop. Both had been plagued with biological
fouling since the systems start-up. While
traditional non-oxidizing biocides had been used
for years, they were expensive, showed marginal
efficacy and always decomposed over time. In fact,
the consistent use of non-oxidizing biocides actually
contributed to fouling of the system and biologically-influenced
corrosion. Oxidizing biocidesbromine and
bleachwere tried in an attempt to remedy
the problem, but they could not be fed at lethal
dosages due to their adverse effect on the inhibitor
formulas and system metallurgy. As a result, mobile
bacteria levels consistently exceeded 1,000,000
(106) colonies per milliliter. Elevated bacteria
levels threatened the systems integrity,
energy efficiency and general hygiene.
Excessive bacteria in the Universitys HVAC
systems not only increased energy consumption,
system waterside corrosion and potential loss
of capital equipmentit posed a serious risk
that students could be exposed to a dangerous
pathogen outbreak. The University tried to solve
the problem by using a variety of industry standard
non-oxidizing biocides that are readily available
to the water treatment service providers. Each
non-oxidizer was chosen for system metallurgy
and treatment program
compatibility. Yet, they all proved ineffective
in terms of cost and efficacy. The organic biocides
eventually decomposed, not only adding to the
organic loading, but serving as a food source
for bacteria growth. In addition, the non-oxidizing
products did not penetrate the slime layers that
formed in the chilled-water loop. As a result,
bacteria levels recovered rapidlywell above
107 colonies per milliliterin the circulated
water. To combat bacterial growth, higher and
higher dosages were applied. Still, efficacy improved
very little and the costs soon became prohibitivemore
than $225,000 per year.
Finally, the University applied bromine and bleach
as a last resort. Low-dose treatments of both
were used to try to stabilize the bacteria without
causing a chemical attack in the high-retention
system. While they were able to stabilize the
bacteria at 106 to 107 colonies per milliliter,
these levels still far exceeded the industry standard
control target of less than 1,000 (103) colonies
per milliliter. The bromine and chlorine residuals
were increased slowly, but the treatment program
inhibitors began to degrade and corrosion rates
jumped. Very little, if any, slime removal was
achieved.
PureLine Treatment Systems resolved the Universitys
problem with a full-service chlorine dioxide shock
feed program that incorporates a pure chlorine
dioxide gas generatorthe P-40E. The P-40E
chlorine dioxide gas generation system produces
a pure gas stream using just one precursorPureCide
(25% sodium chlorite). PureCide is circulated
through a patented electrochemical cell where
it is converted to a chlorine dioxide solution.
The pure chlorine dioxide gas is then stripped
from the solution using proprietary stripping
column. The pure chlorine dioxide gas is immediately
introduced into the water or
air stream to be treated.
Together, PureLines Research & Development
and Engineering & Manufacturing groups designed
a skid-mounted, high-pressure feed system to work
in conjunction with the generator. The portable,
skid-mounted unit allows pure chlorine dioxide
gas to be introduced into the chilled loop. The
innovative system recovers all excess chlorine
dioxide gas and air off the day tank. The excess
chlorine dioxide and air (resulting from stripping
pure chlorine dioxide gas from the anolyte solution)
are recovered from the feed tank and drawn back
into the stripper columns. Since the system recovers
all excess air, there is no need to vent the feed
tank.
The generator and feed skid feature simple and
easy to locate connections for gas, electrical
and plumbing lines. A state-of-the-art programmable
logic controller and relay automatically control
the
on-demand production of chlorine dioxide according
to the chilled water ORP. Interdependent controls
include 14 different fail-safe alarms.
The systems design provides a mobile generation
and high-pressure chlorine dioxide feed system
that is safe enough to operate in an HVAC central
plant. Flexible connections and easy installation
offer a field-friendly solution to a variety of
emergency disinfection applications. In the case
of the thermal energy storage system at the University,
PureLine safely introduced a highly effective
oxidizing biocide that is compatible with existing
treatment formulas. The injection of pure chlorine
dioxide gas has eliminated the addition of solids
and liquids without effecting system pH. PureLines
full-service field technicians were able to install,
start-up, operate, shutdown and remove all equipment
without interrupting the daily activities at the
central plant.
For the first time since it began operating,
bacteria has successfully been reduced to undetectable
levels in the Universitys thermal energy
storage system and chilled water loop. In addition,
corrosion
is no longer a problem, and the University no
longer has to cope with adverse effects on treatment
formulas. PureLines safe and reliable chlorine
dioxide generation technology offers the University
an effective alternative to traditional biocides
without adding unwanted organics, corrosive salts
or outside fluids. Pure chlorine dioxide gas is
a highly efficient kill agent at low dosages and
is completely compatible with existing treatment
program formulations. Chlorine dioxide is also
able to penetrate and eliminate slime formations
without attacking system metallurgy. PureLines
proprietary on-line control system automatically
responds to oxidizer demand, ensuring program
efficacy without jeopardizing treatment formulation
and system integrity.
PureLines patented chlorine dioxide generation
technology, fully-automated controls and dedicated
professional support services, offer a successful
treatment solution that is safe, easy to implement
and non-intrusive even under the constraints typically
found in large central plant facilities. Plant
personnel were finally freed from time-intensive
monitoring and maintenance. Routine system monitoring
now requires less than 10 minutes per day.
PureLines packaged solution is offered under
a full service agreement with the Universitys
total water treatment service provider. The water
treatment service provider is able to offer a
turnkey, hands-off program at desired
margins while reducing the Universitys treatment
costs more than 30% over traditional approaches
used in the past. The savings are even more dramatic
when other positive outcomes such as increased
energy efficiency, treatment efficacy, reduced
unscheduled maintenance, ease of implementation
and extended life span for capital equipment are
all factored into the cost-savings equation. With
unparalleled flexibility, the skid-mounted P-40E
generator is completely portable and allows periodic
shock disinfection treatments to be applied where
and when they are needed.
|